Specialists of the “Institute of Environmental Survey, Planning & Assessment” and “MSU Analytical Centre” have implemented over 200 projects in the field of construction survey, structural engineering, environmental monitoring and scientific research. Due to confidentiality, this section provides information on some of the directions only. The geography of our activities is presented on the map, where numbers match order numbers of projects. Project descriptions are provided after the map in the information table.

# Dates Description Client
209December 2015 - May 2016

Environmental engineering surveys for the construction of the 160 MWe Talahovskaya CHP plant in Sovetsk, Kaliningrad region

ООО «GEOINFORM+»
208December 2015 - May 2016

Environmental engineering surveys for the construction of the 160 MWe Mayakovskaya CHP plant in Gusev, Kaliningrad region

ООО «GEOINFORM+»
207October - November 2016

Technical re-equipment and manufacture reconstruction, Rostov-on-Don, Rostov region. Environmental engineering, geological engineering, hydrometeorological engineering, geodetic engineering surveys, inspection of the footings and bases conditions.

PAO "Rostvertol"
206June - December 2016

Environmental engineering surveys at the "Southern Black Sea" license block ("Vneshnyaya-1", "Olginskaya-1", and "Sochinskaya-1" areas)

ООО «RN-Exploration»
205July - December 2016

Implementation of the background monitoring and ecological-fishery mapping within «Albanovskij», «Varnekskij» and «Zapadno-Prinovozemelskij» license blocks (The Barents Sea)

ООО "RN-Shelf-Arctic"
204June - October 2016

Implementation of the operational satellite monitoring of oil slicks in the Sea of Okhotsk

OOO "Ecoshelf"
203January - July 2016

Implementation of the environmental engineering and aerometeorological surveys for the development of the BD stage project documentaion (Hanhikivi-1 NPP)

AO «TITAN-2 CONCERN» Finnish branch office
202July - August 2016

Reconstruction of a capital construction object (5, Red Square, Moscow) for locating Museum and exhibition complex of the Moscow Kremlin Museums. Hydrometeorological engineering and environmental engineering surveys.

FGUP "ATEKS", FSO of Russia
201October, 2015 – January, 2016

Developing documentation on the reconstruction objects (FGUP "State Research and Development Institute of the Aviation Systems", Moscow)

OAO "Aviaprom"
200December 2014 – October 2015

Developing project documentation (reconstruction, beutification, and landscaping) for an object in Moscow (Kurkino district)

Moscow Department of Natural Resources Management and Environmental Protection
199December 2014 – October 2015

Developing project documentation for an object in Moscow (Klenovy blvd.)

Moscow Department of Natural Resources Management and Environmental Protection
198December 2014 – October 2015

Developing project documentation for an object in Moscow (blvd. at Avtozavodskaya str.)

Moscow Department of Natural Resources Management and Environmental Protection
197October 2014 – December 2015

Integrated engineering survey (Kirinskoe gas condensate field, Sakhalin)

ООО «Krasnoyarskgazprom neftegazproekt»
196February – November 2015

Piles testing (Yamal, Tyumen region)

ООО «MRTS Engineering»
195June – November 2015

Operations environmental monitoring and control at the gas pipeline construction (Nizhegorodskaya region, Mordovia republic)

ООО «Gazprom centerremont»
194October – November 2015

Environmental engineering and hydrometeorological engineering surveys for an object (ОАО «КnААPО», Komsomolsk-na-Amure)

АО «Sibghjektniiaviaprom"
193June 2014 – November 2015

Integrated engineering survey (geodetic, hydrometeorological, geological and environemtnal) for construction objects of the development wells (Astrakhan gas condensate field)

ООО «Krasnoyarskgazprom neftegazproekt»
192June – November 2015

Operational environmental satellite-based monitoring of the water surface (the Sea of Okhotsk)

FBU «Morspassluzhba Rosmorrechflota»
191June - December 2015

Environmental monitoring of the several license blocks (Novy Urengoy, Yamalo-Nenets Autonomous District)

ООО «Gazprom dobycha Urengoy»
190June - December 2015

Environmental engineering, aerometeorological engineering and hydrological engineering surveys for the development of project documentation ("Hanhikivi-1" NPP), Finland

AO "Project Management"
189March - August 2015

Integrated engineering surveys for the construction objects (assembly department and flight test facility), Voronezh

PAO “Voronezh joint-stock aircraft manufacturing company”
188May - October 2015

Integrated engineering surveys for the development of project documentation for the construction of CHPP-22 main building (Dzerzhinsky, Moscow region)

ООО «GEOINFORM+»
187November 2014 – January 2015

Environmental engineering and hydrometeorological engineering surveys, development of a section for project documentation, for a manufacturing unit (Moscow)

AO “Sibproektniiaviaprom”
186September - December 2014

Engineering surveys for an object (IMK LCO complex) reconstruction, Akhtubinsk, Astrakhan region

ZAO “Kazan Giproniiaviaprom”
185September-November 2014

Engineering surveys and inspection of buildings footings for an object in Moscow (7, Victorenko str.)

FGUP “State Scientific and Research Institute of Aviation Systems”
184September - December 2014

Environmental engineering surveys and the development of the recultivation project for the "PGU-СHPP" object  in Yaroslavl

ZAO "ENSI"
183August - December 2014

Assessment of the background environmental conditions, and environmental and fishery mapping of the Kara Sea license blocks

OOO “Krasnoyarskgazprom neftegazproekt”
182August - November 2014

Geotechnical monitoring of the OAO "Gazprom" railroad infrustructure objects, the Yamalo-Nenets Autonomous District

ООО «Gazpromtrans»
181August - September 2014

Engineering surveys for an object (1, Letnaya str., Dolgoprudny, Moscow region)

OAO “Stavropolskiy Electronproekt”
180August - September 2014

Technical inspection of the supporting structures of OAO "VDNH" Pavilions NN 1, 32, 34, 58

OAO “National Economy Achievement Exhibition”
179July 2014 – March 2015

Lab analysis of the frozen soils (En-Yakhinskoe gas condensate field, Purovsky region, Yamalo-Nenets Autonomous District)

PAO “VNIPIgazdobycha”
178July - September 2014

Lab analysis of the multiyear frozen soils (Labaganskoe oil field, Nenets Autonomous District)

OOO “NK “Rosneft – NTC”
177July - August 2014

Lab analysis of the physical and mechanical properties of the multiyear frozen soils (Suzunskoe oil field, Krasnoyarsk region)

OOO “NK “Rosneft – NTC”
176July - August 2014

Lab analysis of the physical and mechanical properties of the multiyear frozen soils (Suzunskoe oil field, Krasnoyarsk region)

OOO “NK “Rosneft – NTC”
175July - August 2014

Engineering surveys for an object (OAO "Stupinskoe machine-building plant", Stupino, Moscow region)

ZAO “Kazan Giproniiaviaprom”
174June - December 2014

Updating of the project documentation for an object (area between Djamgar pond and Perlovskoe cemetery, Moscow)

Moscow Department for realization projects in ecology and forestry
173May - September 2014

Lab analysis of the multiyear frozen soils (Novoportovskoe oil and gas condensate field)

OAO “Giprotyumenneftegaz”
172May - September 2014

Integrated lab analysis of the multiyear frozen soils (Russkoe field)

OAO “Giprotyumenneftegaz”
171April - June 2014

Lab analysis of the multiyear frozen soils (Vankorskoe oil field)

OAO “Giprotyumenneftegaz”
170April - June 2014

Engineering surveys for an object (aerodrome base Voronezh "Pridacha")

ZAO “Kazan Giproniiaviaprom”
169April - July 2014

Environmental engineering surveys for the construction project (Pashino, Novosibirsk region, object 20/155-21)

ОАО «12 Voenproekt»
168April - June 2014

Development of project documentation for capital repairs of the road and path net (Vorob'evy Gory, Moscow)

Gorky Central Recreation and Leisure Park
167April - May 2014

Environmental engineering surveys at Museon Park (2, Krymsky Val, Moscow)

Moscow Association for Museam and Exhibition Work
166February - May 2014

Engineering surveys for a project (OAO Utes, Ulyanovsk region)

ZAO “Kazan Giproniiaviaprom”
165February - June 2014

Geological engineering and environmental engineering surveys for an object (28 Olkhovskaya str., 21 Zhukov proezd, Moscow)

OOO “Stroy Garant”
164January - March 2014

Scientific research on the topic (calculation of survey parameters for the operational and post-processing interpretation of seismoacoustic data)

OOO "Split"
163December 2013 – January 2014

Development of a section for project documentation (gas pipeline "South Stream")

AO “Giprospetsgaz”
162December 2013 – March 2014

Engineering surveys and inspection of the building structures for an object (PAO “Voronezh joint-stock aircraft manufacturing company”, Voronezh)

PAO “Voronezh joint-stock aircraft manufacturing company”
161December 2013 - May 2014

Geological engineering, hydrogeological engineering, geotechnical engineering surveys for an object (Yazhno-Tambeisky gas condensate field, Yamalo-Nenets Autonomous District, Tyumen region)

OAO "Zarubezhenergoproekt"
160December 2013 – June 2014

Development of project documentation for an object (territory PК № 146-SVAO between Yablochkova str. and Moscow railroad, Moscow)

Moscow Department for realization projects in ecology and forestry
159December 2013 – June 2014

Development of project documentation for an object (territory PК № 134-SVAO between Yablochkova str. and Moscow railroad, Moscow)

Moscow Department for realization projects in ecology and forestry
158October - December 2013

Engineering surveys for an object (Belozersky, Voskresensky district, Moscow region)

ZAO “Kazan Giproniiaviaprom”
157October - December 2013

Engineering surveys for an object (OAO "Perm engine plant", Perm)

ZAO “Kazan Giproniiaviaprom”
156October - December 2013

Engineering surveys for an object (OAO "STAR", 140a, Kuibysheva str., Perm)

ZAO “Kazan Giproniiaviaprom”
155October - December 2013

Engineering surveys for an object (OAO "ONPP"Technology", Obninsk, Kaluga region)

ZAO “Kazan Giproniiaviaprom”
154October - December 2013

Engineering surveys for an object (OAO "ONPP"Technology", Obninsk, Kaluga region)

ZAO “Kazan Giproniiaviaprom”
153September - November 2013

Environmental engineering and geological engineering surveys for an object (15. Marshala Timoshenko str., Moscow)

ООО «Hited-Energetika»
152September - December 2013

Lab analysis of the physical and mechanical properties of the frozen soils (gas pipeline "Power of Siberia", Yakutia Republic)

PAO “VNIPIgazdobycha”
151September 2013 - March 2014

Development of project documentation for the environmental protection of the objects under capital repairs (OOO "Gazprom transgaz Saint-Petersburg", Leningrad region, Novgorod region, Tver region, Smolensk region, Pskov region, Kaliningrad region)

OOO "Gazprom transgaz Saint-Petersburg"
150September 2013 - July 2015

Operations environmental monitoring during the construction of the 3rd stage objects (Chayandinskoe oil and gas condenstae field, Yakutiya Republic)

OOO “Gazprom dobycha Noyabrsk”
149September 2013 - March 2016

Operations environmental monitoring during the construction of 1st and 2nd stage objects (Chayandinskoe oil and gas condenstae field, Yakutiya Republic)

OOO “Gazprom dobycha Noyabrsk”
148August - December 2013

Environmental engineering and geological engineering surveys for an object (main gas pipeline, Nizhne-Kvakchinskoe gas condensate field, Kamchatka region).

OAO “SevKavNIPIgaz”
147July - October 2013

Geodetic engineering, environmental engineering, hydrometeorological engineering, geological engineering surveys for several objects (OAO  “Tactical Missiles Corporation”, Korolev, Moscow region)

OAO “Tactical Missiles Corporation”
146June - November 2013

Environmental impact assessment, environmental engineering surveys, geological engineering surveys, inspection of building structures, measuring activities for OAO “I.I. Toropov State mechanic and engineering bureau “Vympel” production.

OAO “I.I. Toropov State mechanic and engineering bureau “Vympel”
145June - August 2013

Lab analysis of the multiyear frozen soils (intrafield oil pipeline UPN "Labaganskaya" - DNS "Nadeiyuskaya", Nenets Autonomous District)

OOO “NK “Rosneft – NTC”
144June - September 2013

Radiological research, noise measurement, development of the mapping materials for an object (depot construction, Adler, Sochi, Krasnodar region)

ZAO “Ecological safety of industry, energetics and transport”
143June - August 2013

Development of project documentation, and environmental engineering surveys for an object in Moscow (Aleshinka creek floodplain, Marushkinskoe, Moscow)

OOO "MEGAPARK"
142June 2013 - October 2014

Operations environmental monitoring during the construction of objects (a part of the № 4 КС-15 manufactory reconstruction)

OOO "Gazprom centerremont"
141May 2013 - October 2014

Operations environmental monitoring during the construction of the "Pisarevka" object (a part of the "Urengoy-Novopskov" gas pipeline reconstruction)

OOO "Gazprom centerremont"
140May 2013 - October 2014

Operations environmental monitoring during the construction of the "Bubnovka" object (a part of the "Urengoy-Novopskov" gas pipeline reconstruction)

OOO "Gazprom centerremont"
139May 2013 - October 2014

Operations environmental monitoring during the construction of the "Ekaterinovka" object (a part of the "Urengoy-Novopskov" gas pipeline reconstruction)

OOO "Gazprom centerremont"
138April - June 2013

Engineering surveys for an object (PCM blades and details development shop, OAO "Mil Moscow helicopter plant", Tomilino, Moscow region). Geodetic engineering, geological engineering, environmental engineering, hydrometeorological engineering surveys.

ZAO “Kazan Giproniiaviaprom”
137April - June 2013

Lab analysis of the physical and mechanical properties of the multiyear frozen soils (Vankorskoe oil field, Krasnoyarsk region)

OOO “NK “Rosneft – NTC”
136April - June 2013

Arrangement of the Vankorskaya cluster of fields (Krasnoyarsk region). Reconstruction of the oil wells cluster pads №№ 1, 2, 3, 4, 14, 15, 16, 101, 110, 111, 112. Lab analysis of the physical and mechanical, and thermophysical  properties of the multiyear frozen soils.

OOO “NK “Rosneft – NTC”
135April - June 2013

Arrangement of the Vankorskaya cluster of fields (Krasnoyarsk region). Reconstruction of the cluster pads №7,20,21,24,108,109, ВДК1,2,3,4,5,6,7. Lab analysis of the physical and mechanical, and thermophysical  properties of the multiyear frozen soils.

OOO “NK “Rosneft – NTC”
134April - May 2013

Developing a chapter for the project documentation ("Impact assessment and damage evaluation for the biological water resources", objects construction at Pavlovsk deposit).

PermNIPIneft – ООО «Lukoil engineering» branch
133March - June 2013

МТЦ М-2 construction (bld 18, bld 16, 3, Leningrad road, Moscow). Inspection of the technical conditions of the buildings located within the affected area of the new construction.

ZАО «Gendirectsia «Center»
132March - May 2013

Environmental engineering surveys for a project (FGUP “Gas-turbine engineering research and production center “Salut”, Belozersky, Voskresensky district, Moscow region)

FGUP “Gas-turbine engineering research and production center “Salut”
131March - May 2013

Engineering surveys, measuring operations, and engineering inspection of the supporting constructions and enclosing structures of the LIS building, "Severny" airdrome (Rostov-on-Don). Geological engineering, environmental engineering, and hydrometeorological engineering surveys.

ZAO “Kazan Giproniiaviaprom”
130March - May 2013

Integrated site improvements of the Moscow settlement territory. Development of the working project for the improvements and amenity planting; environmental engineering surveys.

Administration of the Moskovsky settlement
129February - June 2013

Residence hall construction (Lomonosov MSU, for 5000 students). Moscow, new campus part at the Leninskie Gory. Geological engineering and environmental engineering surveys.

OOO “ISK “FORT”
128December 2012 - December 2014

Operations environmental monitoring and control over compliance with the environmental legislation requirements during construction of an object ("Gas pipeline intersection "Kubanskaya - Korenovskaya" of the South-European gas pipeline).

OOO “Gazprom invest”
127December 2012 - September 2013

Engineering surveys for a project ("Reconstruction and technical re-equipment of the OAO "NAZ SOKOL" flight-test structure, Nizhny Novgorod). Geodetic engineering, environemental engineering, geological engineering, and hydrometeorological engineering surveys.

ZAO “Kazan Giproniiaviaprom”
126December 2012 - October 2013

Lab analysis of the physical and mechanical, and thermophysical properties of the multiyear frozen soils (Kharasavey gas condensate field, Yamalo-Nenets Autonomous District)

PAO “VNIPIgazdobycha”
125December 2012

Development of project documentation for the yard area redevelopment (Perovo district, Moscow)

GKU "Engineering service for Perovo district"
124November 2012 - March 2013

Engineering surveys for a project ("Reconstruction of the Taganrog "Yuzhny" airdrome base (the Rostov region)"). Environmental engineering, geological engineering, and hydrometeorological engineering surveys.

AO “Kazan Giproniiaviaprom”
123November 2012 - February 2013

Geological engineering survey for the industrial warehouse structure construction (Northern industrial area, near Academic Grushin str., Khimki, Moscow region)

ZAO "DENIZ Development"
122November 2012 - February 2013

Engineering surveys for a project (reconstruction of the Ulyanovsk "Vostochny" airdrome base). Environmental engineering, geological engineering, and hydrometeorological engineering surveys.

ZAO “Kazan Giproniiaviaprom”
121November - December 2012

"Underground reservoirs for drill mud disposal at the Bovanenkovskoe gas condensate field" (Yamalo-Nenets Autonomous District). Development of the following sections: "Environmental impact assessment", "Allowable emissions project", "Project for the waste generation norms and limits for their disposition".

ООО «Podzemgazprom»
120November 2012 - June 2013

Construction of a hotel with apartments and cultural and entertaining complex (15, Druzhinnikovskaya str., Moscow). Environmental engineering and geological engineering surveys.

ООО «Integral Union»
119October 2012 - October 2013

Operations environmental monitoring and control over compliance with the environmental legislation requirements during construction of an object (reconstruction of the KC Taezhnaya of the Yamburg - Western boundary pipeline, Khanty-Mansiisk autonomous district).

OAO “Gazprom centrremont”
118October - December 2012

Testing facilities for helicopter engines VK-2500 OAO "UMPO" (Ufa, Republic of Bashkortostan)

ОАО «Ufimskoe motor-building production association»
117October - December 2012

Engineering surveys for a project (technical re-equipment of the manufacturing building OAO "NPP "MOTOR", unit 61, Ufa, Republic of Bashkortostan). Geodetic engineering and geological engineering surveys.

ОАО «NPP «MOTOR»
116October - December 2012

Radiological research for the construction of the combined road (vehicle road/railroad) Adler - "Alpica-Service" alpine resort.

ZAO “Ecological safety of industry, energetics and transport”
115October - December 2012

Reconstruction of a bench-scale structure (complex of the laboratory bench tests for the aircraft systems and equipment). ОАО «Sukhoy Company», Moscow. Buildings 1, 2, 3, 3а, 6, 7, СТН-10, 16а, 37а, 62. Environmental engineering and geological engineering surveys.

ОАО «Sukhoy Company»
114October - November 2012

Reconstruction and technical re-equipment of the FGUP «GosNIIAS» objects, Moscow. Environmental engineering and geological engineering surveys.

FGUP «GosNIIAS»
113September - December 2012

Supporting operations for the fieldwork part of the project "Investigation of the eliminated well heads at the Harasavey-sea section"

ООО «Piter Gas»
112September - December 2012

Supporting operations for the fieldwork part of the project, hydrobiological research, office analysis of the field data, and report preparation (project: "Investigation of the eliminated well heads at the aquatories of the Ob and Taz Bays of the Kara Sea")

OOO "Piter Gas"
111September - December 2012

Reconstruction of the testing complex (Kirzhach, the Vladimir region). Environmental engineering, hydrometeorological engineering, geodetic engineering, geological engineering surveys, and sanitary protection zone project.

FGUP "Scientific and research institute of parachute construction"
110September - December 2012

3D computer modelling of an air blast as a result of an object explosion (С-1 reactor unit separator)

ООО «Lukoil-Nizhegorodniinefteproekt»
109September 2012 - October 2013

Operations environmental monitoring during the construction of objects "Arrangement of the Yubileynoe gas condensate field (АУ 11 and ПК 18-20 layers)

OOO “Gazprom dobycha Nadym”
108September 2012 - December 2013

Obtaining permissions for building the areas of deposits during the construction of a range of objects (part of the main gas pipeline Bovanenkovo - Ukhta system).

ZAO “Yamalgazinvest”
107August 2012 - December 2016

Operations environmental monitoring and control over compliance with the environmental legislation requirements during construction of objects within the "Expanding the unified system of gas supply for providing gas supply to the South Stream pipeline" construction project

OOO “Gazprom invest”
106August 2012 - December 2015

Operations environmental monitoring and control over compliance with the environmental legislation requirements during construction of objects within the "The unified Bovanenkovo - Ukhta system of gas supply" construction project.

ZAO “Yamalgazinvest”
105July 2012 - August 2013

Operations environmental monitoring and control over compliance with the environmental legislation requirements during construction of objects: "Reconstruction of the compressor department N4 RC-12 Mikun'" (Komi Republic), "Reconstruction of the KC Nizhneturinskaya" (Sverdlovsk Region), "Reconstruction of the refrigerant bulk plant" (Yamalo-Nenets Autonomous District).

OAO “Gazprom centrremont”
104July - December 2012

Geological engineering and environmental engineering surveys for an object ("Reconstruction of the ОАО «KUZNETSOV» manufacturing and testing facility", Samara)

ОАО «KUZNETSOV»
103July - November 2012

Environmental engineering for an object (new cemetery, m. Verkhny Chov, Syktyvkar, Komi Republic)

Syktyvkar administration
102June - July 2012

Development of a section for project documentation - environmental protection, environment impact assessment - for an object ("Construction and arrangement of the wells of the Dorokhovskoe oil field")

PermNIPIneft – ООО «Lukoil engineering» branch
101May - December 2012

Engineering surveys for an object within the "Oil pipeline construction at the Polaznenskoe oil field", Perm kray. Environmental engineering, hydrometeorological engineering, geodetic engineering, geological engineering, geophysical engineering surveys, diving operations.

PermNIPIneft – ООО «Lukoil engineering» branch
100May 2012 - December 2013

Implementation of the geotechnical monitoring for the construction of objects within "The unified Bovanenkovo - Ukhta system of gas supply" construction project («КС-2 «Yarynskaya». КЦ-1», «КС-3 «Gagaratskaya». КЦ-1», «КС-4 «Vorkutinskaya». КЦ-1», «КС-5 «Usinskaya». КЦ-1», «КС-6 «Intinskaya». КЦ-1», «КС-7 «Syninskaya». КЦ-1», «КС-8 «Chikshinskaya». КЦ-1», «КС-9 «Maloperanskaya». КЦ-1», «КС Vorkutinskaya – КС Yarynskaya» vehicle road).

ZAO “Yamalgazinvest”
99May 2012 - December 2013

Implementation of the geotechnical monitoring for the construction of objects within "The unified Bovanenkovo - Ukhta system of gas supply" construction project ("Line pipe, line 1, кm 28,0/0 – кm 111,7", «КС-1 «Baydaratskaya». КЦ-1», «Line pipe, line 1, кm 111,7 – кm 186,7», «Line pipe, line 1, km 186,7 – кm 526,7», «Line pipe, line 1, кm 526,7 - кm  860,5»).

ZAO “Yamalgazinvest”
98April - May 2012

Development of the project documentation for the improvements of a pond with surroundings (3-5, Krasny Kazanets str., Moscow)

Engineering service of the Veshnyaki district
97April - May 2012

Reconstruction and technical re-equipment of the ОАО «Central design bureau of automatics» manufacturing structure (Omsk). Environmental engineering and hydrometeorological engineering surveys.

ОАО «Central design bureau of automatics»
96March - October 2012

Operations environmental monitoring during an object construction ("Line pipe, line 1, кm 111,7 – кm 186,7") within "The unified Bovanenkovo - Ukhta system of gas supply" construction project in 2012 (Yamalo-Nenets Autonomous District).

OOO "Piter Gaz"
95March - April 2012

Reconstruction and technical re-equipment of the OAO “Ryazan engineering bureau “Globus” testing facility (6, Vysokovoltnaya str., Ryazan). Integrated geodetic engineering, geological engineering, environmental engineering and hydrometeorological engineering surveys.

OAO “Ryazan engineering bureau “Globus”
94December 2011 - March 2012

Modernization of the Enem2-Shendjiy and Shendjiy-Psekups railway tracks (Republic of Adygeya). Radiological and environmental engineering, and landscape surveys.

ZAO “Ecological safety of industry, energetics and transport”
93December 2011 - March 2012

Modernization of the Afapostik-Chinary, Poltavskaya-Protoka, Konokovo-Ovechka, Komsomol'skaya-Tverskaya, Psekups-Saratovskaya, and Armavir-Kara-Dzhalka railway tracks (Krasnodar Territory). Radiological and environmental engineering, and landscape surveys.

ZAO “Ecological safety of industry, energetics and transport”
92December 2011 - March 2012

Modernization of the Bogoslovskaya-Zelenchyuk, Zelenchyuk-Kian, Zelenchyuk-Nevinomysskaya, Ovechka-Bogoslovskaya, Suvorovskaya-Minvody railway tracks (Stavropol Territory). Radiological and environmental engineering, and landscape surveys.

ZAO “Ecological safety of industry, energetics and transport”
91June - December 2011

Radiological surveys and soil surveys at the object "Cable way 3S from theconfluence of Mzymta and Pslukh rivers to the finish area of the Rosa Khutor ski resort, from the finish area of the Rosa Khutor ski resort to the Mountain olympic village" (Sochi, Krasnodar Territory)

ZAO “Ecological safety of industry, energetics and transport”
90December 2011 - January 2012

Reconstruction and technical re-equipment of the OAO "Krasny gidropress" heat-treatment, forge-and-pressing, casting, galvanizing, and blank sections (Taganrog, Rostov Region). Environmental engineering and hydrometeorological engineering surveys.

OAO “Tactical Missiles Corporation”
89November 2011 - February 2012

Reconstruction of the И-21 debugging system structure (Akhtubinsk, Astrakhan Region). Integrated geodetic engineering, geological engineering, environmental engineering, and hydrometeorological engineering surveys.

FGUP «GosNIIAS»
88November - December 2011

Inspection of the technical condition of the building constructions (44, 88, and 94 bld 1, Leningradskoe shosse, Moscow) within the "Reconstruction of the Leningradskoe shosse from "Sokol" underground station to Moscow Ring Road" project.

OAO “Mosinzhproekt”
87November 2011 - June 2012

Implementation of the planning and surveying works for creating the natural complex №85-North-East Administrative District, located in the Yauza river valley along the Tenisty road (Moscow). Development of the beautification and landscaping project.

Prefecture of Moscow North-East Administrative District
86November 2011 - June 2012

Implementation of the planning and surveying works for creating the natural complex №74-North-East Administrative District, located in the Chermyanka river valley (Moscow). Development of the beautification and landscaping project.

Prefecture of Moscow North-East Administrative District
85November 2011 - June 2012

Reconstruction of the FGUP "Scientific and research institute of parachute construction" testing complex (Kirzhach, Vladimir Region). Environmental engineering, geological engineering, geodetic engineering, and hydrometeorological engineering surveys. Development of the section "List of actions for the environmental protection", development of the sanitary protection zone.

OAO “Aviaprom”
84September - December 2011

Development of a dry-cargo area in the Taman' sea port (Krasnodar Territory). Hydrometeorological engineering survey.

OOO “TransProekt”
83September - October 2011

Integrated assessment of the key marine environment and biota parameters at the "Western Black Sea" license block (Black Sea, Russian and Abkhazian sectors)

P.P.Shirshov Institute of Oceanology
82September - October 2011

Technical re-equipment and reconstruction of the manufacturing building of mechanical and heat treatment and control over heat-stable nickel alloys (Moscow). Geodetic engineering, environmental engineering, and hydrometeorological engineering surveys.

OAO “All-Russia Institute of Light Alloys”
81July - October 2011

Operations environmental monitoring during an object construction ("Line pipe, line 1, кm 111,7 – кm 186,7") within "The unified Bovanenkovo - Ukhta system of gas supply" construction project in 2011 (Yamalo-Nenets Autonomous District).

OOO "Piter Gaz"
80July - September 2011

Technical re-equipment (reconstruction) of the manufacturing and testing facility (item 27) (OAO “I.I. Toropov State mechanic and engineering bureau “Vympel”, Astrakhan Region). Geodetic engineering, environmental engineering, and geological engineering surveys.

OAO “I.I. Toropov State mechanic and engineering bureau “Vympel”
79June - August 2011

Radiological, and geological and geomorphological research (investigation of the dangerous exogenous geological processes) at several objects in Sochi, Krasnodar Territory.

ZAO “Ecological safety of industry, energetics and transport”
78June - August 2011

Reconstruction and technical re-equipment of the GNC FGUP "Keldysh Center" experimental and production complex (Moscow). Environemental engineering and geological engineering surveys.

AO “Kazan Giproniiaviaprom”
77June - August 2011

Reconstruction and technical re-equipment of the OAO "Tekhpribor" production areas and testing base, bld. 10 (St. Petersburg). Environmental engineering, geological engineering, and hydrometeorological engineering surveys.

ОАО «Tekhpribor»
76June - October 2011

Reconstruction of the energy unit № 2 of OAO "OGK-b" Ryazanskaya GRES branch, with the major equipment replacement (Novomichurinsk, Ryazan Region)

ОАО «Zarubezhenergoproekt»
75January - May 2011

Integrated engineering surveys for a project. OAO "Mosenergo" branch. Construction of the ПГУ-420Т energy unit (Moscow). Geological and hydrogeological engineering surveys for the construction project.

ОАО «Zarubezhenergoproekt»
74April 2011 - December 2012

Development of the environment-oriented sections of the project documentation for an object ("Extension of the RF unified system of gas supply for supplying gas to the "South Stream" gas pipeline"). Sections developed: "List of actions for the environmental protection", "Environmental impact assessment", "Land remediation", "Materials for the public hearings".

ZAO NPF «DIEM»
73April - October 2011

Archeological investigations for the integrated marine engineering surveys within the marine part of the "South Stream" project (Black Sea, exclusive economic zone and Bulgarian territorial waters).

OOO "Piter Gaz"
72February - October 2011

Oceanographical, chemicoanalytical, hydrobiological, ornithological and theriological investigations within the environmental engineering survey at the marine part of the "South Stream" gas pipeline (Russian, Turkish, Bulgarian sectors of the Black Sea).

OOO "Piter Gaz"
71December 2010 - December 2012

Environmental engineering surveys for collecting background data for the development of the project documentation within the framework of the investment project "Expansion of the unified system of gas supply for supplying gas to the "South Stream" gas pipeline" (Voronezh Region, Rostov Region, Nizhny Novgorod Region, Republic of Mordovia, Saratov Region, Volgograd Region).

ZAO NPF «DIEM»
70November 2010 - April 2011

Implementation of the land-use planning works for the registration of rights to use water reserve land for the construction of the objects: "кm 1106,0 – кm 1239,0 section", "кm 1239,0 – кm 1361,0 section", "кm 1361,0 – km 1478,6 section" within the "Ukhta - Torzhok main gas pipeline system (phase 1)" construction project (within the Republic of Komi boundaries)

ZAO “Yamalgazinvest”
69April - May 2011

Reconstruction of the federal road М-3 "Ukraine" - from Moscow via Kaluga, Bryansk, to the border with Ukraine (Moscow Region, Kaluga Region) - with the further exploitation on a fee paid basis. Radiological research and negative physical impacts measurements (noise, electromagnetic field) as a part of the environmental engineering survey.

ZAO “Ecological safety of industry, energetics and transport”
68April - May 2011

Capital repairs of the green area in the Yauza floodplain along Severodvinskaya str. (Moscow). The entire set of the design and survey work implemented; the project documentation for the public garden improvements developed and approved.

Prefecture of Moscow North-East Administrative District
67February - May 2011

Construction of the administrative office building (14 (estate), Kozhevnicheskaya str., Moscow). Five monitoring cycles of the subsidence of building constructions located within the area of the construction influence, and one monitoring cycle of the horizontal displacement of the shoring of excavation of the constructed administrative office building.

OOO UK “Progress-Finance”
66January - February 2011

Reconstruction and technical re-equipment of the complexes for investigations, development, and testing of the aircraft materials, coversheets, and technologies, 2nd stage, within the framework of the agreement between FGUP "VIAM" and Ministry of Industry and Trade of the Russian Federation (Moscow). Environmental engineering and radiological engineering surveys.

OAO “Stavropolskiy Electronproekt”
65December 2010 - May 2011

Reconstruction of Dmitrovskoe shosse: "Transport junction at the crossing with Nizhnelikhoborsky str." (Moscow). Shoring of neighbouring buildings foundations project developed. Program of geodetic monitoring of the buildings and constructions located within the affected area developed.

OAO “Mosinzhproekt”
64March - April 2011

Construction of the hotel building: 74 (estate), Gilyarovskogo str., Moscow. A set of the design and survey work implemented, including development of the projected hydrogeological conditions change, development of the shoring of excavation, calculation of the influence of the hotel building on the surrounding constructions, and calculation of the progressive hotel building collapse.

OOO “Intex City Group"
63March - April 2011

Reconstruction and technical re-equipment of a sector for producing inertial position navigation systems, and temperature-controlled mechanical sector of the OAO Tambov plant “Elektropribor” processing center (Tambov). Engineering surveys for the reconstruction and technical re-equipment of the existing industry.

OAO Tambov plant “Elektropribor”
62October 2010 - April 2011

Construction of objects: "Pochinki - Yaroslavl sector, кm 195,1 – кm 220,1, кm 250,1 – кm 267,5, кm 267,5 – кm 323,0" within the "Pochinki - Gryazovets gas pipeline" construction project (Vladimir Region, Nizhny Novgorod Region). A set of the land-use planning works for the registration of rights of ZAO “Yamalgazinvest” to use water reserve land at the parts of the Vladimir and Nizhny Novgorod Regions water objects.

ZAO “Yamalgazinvest”
61February - March 2011

Re-equipment and reconstruction of the research and testing center, and manufacturing base for aerodynamics and integrity FGUP "CAGI" (Zhukovsky, Moscow Region). A set of engineering surveys.

ZAO “Kazan Giproniiaviaprom”
60December 2010 - February 2011

Construction of a pharmaceutical factory ("TEVA" production) in the south-eastern part of the Frunzensky district of Yaroslavl (Yaroslavl Region). Environmental engineering surveys at the justification of investments stage.

The Environmental Fund for Urban Development «ECOGOROD»
59June 2010 - January 2011

Replacement of the finite area of the main Yaroslavl-Moscow oil pipeline, 283-314 km. Re-equipment (Moscow, Moscow Region). Environmental engineering surveys; development of the "List of actions for the environmental protection" chapter.

OAO “Giprotruboprovod”
58December 2010 - January 2011

Construction of the M-5 "Ural" road - from Moscow via Ryazan, Penza, Samara, Ufa to Chelyabinsk at the bypassing area (Oktyabrskiy settlement) with a bridge across the Moscow river, кm 28 – кm 37 (Moscow Region). Geological engineering surveys for the construction project.

OAO “Proekttransstroy”
57November - December 2010

Site improvements in a park at the crossing of Dezhnev str. and Urlovskiy str. for organization of the IX district flower beds festive (Moscow). Implementation of the entire set of the design and survey works; development and approvement of the project documentation.

Prefecture of Moscow North-East Administrative District
56November - December 2010

Reconstruction of the "Srednevolzhskiy steel production plant" with installation of the hot dipped galvanizing line («SIRIO») in the new building, including projection of the extension and the insertion between buildings (Novosemeykino, Krasnoyarskiy district, Samara Region). A set of engineering surveys.

Srednevolzhskiy steel production plant
55November - December 2010

Construction of an object: "Overhead line from the "Psou" electrical substation to the "Adler" substation, from the "Adler" substation to the "Kudepsta" substation, from the "Kudepsta" substation to the "Khosta" substation (Sochi, Krasnodar Territory). Radiological research within the environmental engineering survey project.

ZAO “Ecological safety of industry, energetics and transport”
54November - December 2010

Construction of an object: "Overhead line for power delivery from the Sochi thermal power station to the "Sochi" substation, from the "Sochi" substation to the "Pasechnaya" substation, from the "Pasechnaya" substation to the "Dagomys" substation" (Sochi, Krasnodarskiy Territory). Radiological research within the environmental engineering survey project.

ZAO “Ecological safety of industry, energetics and transport”
53November - December 2010

Construction of objects OOO «Gazprom transgaz Tomsk»: "Distribution gas pipeline between "Zarya" gas-distributing plant and "Plotnikovo" gas-distributing plant", "Distribution gas pipeline from Nizhnevartovskaya GRES gas-distributing plant to the Izluchinsk settlement boilerhouse v/ch 1020", "Distribution gas pipeline between "Sokur" gas-distributing plant and v/ch 1020 gas-distributing plant" (Tomsk Region). Environmental engineering surveys.

ООО «Gazprom transgaz Tomsk»
52November - December 2010

Reconstruction and re-equipment of the OAO "Krasniy gidropress" manufacture (Taganrog, Rostov Region). A set of engineering surveys implemented.

OAO “Tactical Missiles Corporation”
51November - December 2010

Construction of the bulk fuel installations at the OAO “Tactical Missiles Corporation” territory (Akhtubinsk, Astrakhan Region). A set of engineering surveys implemented.

OAO “Tactical Missiles Corporation”
50November - December 2010

Re-equipment and reconstruction of the ОАО «Moscow radio manufacturing plant «Temp» radio manufacture (59 (estate), Kavkazskiy blvd., Moscow). A set of engineering surveys implemented.

ОАО «Moscow radio manufacturing plant «Temp»
49November - December 2010

Reconstruction of the OAO “Azov optical mechanics plant” manufacture, foundry production (Azov, Rostov Region). A set of engineering surveys implemented.

OAO “Tactical Missiles Corporation”
48October - December 2010

Project for the development of a radioactive waste burial facility in the "Sapfir" object buried tanks (Krasnoyarsk Territory). Design works for the development of a "List of actions for the environmental protection" chapter implemented; recommendations in terms of solution of environmental issues during development of the radioactive waste burial facilities developed.

ОАО «VNIPIpromtechnologii»
47February - December 2010

Construction of an object ("Extraction of a sludge line 600 mm out of the construction area (from Mar'ino station to Zyablikovo station of the Lyublinsko-Dmitrovskaya line, Moscow Metro)"). A set of engineering surveys implemented; "List of actions for the environmental protection" chapter developed.

ООО PSK «ASTA»
46August - December 2010

Construction of an object ("Extraction of the utility lines out of the construction area (from Novogireevo station to Novokosino station of the Kalininskaya line, Moscow Metro)"). A set of engineering surveys implemented; "List of actions for the environmental protection" chapter developed.

ООО PSK «ASTA»
45November 2010

Construction of an object ("Yuzhno-Shapkinskoe - Khar'yaga gas pipeline" (Nenets Autonomous District)). Lab analysis of the physical and mechanical, and thermophysical properties of the multiyear frozen soils within the geological engineering surveys.

ОАО «Kirovvodproekt»
44September - November 2010

Construction of an object (Gas pipeline "Kirinskoe gas condensate field onshore production facility - "Sakhalin" gas pipeline"). Environmental engineering surveys; development of the cartographic material.

ZAO NPF «DIEM»
43August - November 2010

Construction of the Kankunskaya HPP at the Timpton river (Yakutiya Republic). Environmental engineering surveys within the set of works for the environmental impact assessment.

ОАО «NIPII ET «ENERGOTRANSPROEKT»
42September - October 2010

Site improvements along Yaroslavskoe shosse, from bld. 118 to bld. 124 (Moscow). The entire set of the design and survey work implemented; the project documentation for site improvements developed and approved.

Prefecture of Moscow North-East Administrative District
41August - September 2010

A set of engineering surveys for the construction of a new OAO “A.Y. Bereznyak State mechanic and engineering bureau “Raduga” manufacturing unit (Dubna, Moscow Region).

OAO “A.Y. Bereznyak State mechanic and engineering bureau “Raduga”
40August - September 2010

Reconstruction and re-equipment of the operating instrument-making facility OAO “State research and development enterprise “Region” (13A (estate), Kashirskoe shosse, Moscow). A set of engineering surveys implemented.

OAO “State research and development enterprise “Region”
39May - September 2010

Construction of an object "Yaroslavl - Gryazovets sector, кm 80,0 – кm 174,0" within the "Pochinki - Gryazovets gas pipeline" construction project (Yaroslavl Region). Implementation of the land-use planning works for the registration of rights of ZAO “Yamalgazinvest” to use water reserve land for the construction of the object.

ZAO “Yamalgazinvest”
38June - August 2010

Construction of objects: ""Gribovo" 750 kV substation, "Dorokhovo" 500 kV substation, Gribovo - Dorokhovo 500 kV HV line" within the "Kalininskaya NPP - Gribovo 750 kV HV line" construction project (Mozhayskiy district, Volokolamsliy district, Moscow Region). Geological engineering and environmental engineering surveys implemented.

ОАО «NIPII ET «ENERGOTRANSPROEKT»
37June - August 2010

A set of the geological engineering, environmental engineering, and hydrometeorological engineering surveys at the area of Novomoskovskaya GRES extension.

OAO "Zarubezhenergoproekt"
36June 2010

Environmental engineering surveys at the re-equipment and reconstruction areas of the OAO “Tactical Missiles Corporation” manufactuing (Korolev, Moscow Region).

OAO “Tactical Missiles Corporation”
35May - June 2010

Developing a chapter "List of actions for the environmental protection" within the mixed-use residential cluster construction project (Nametkina str. and Khersonskaya str. crossing, Moscow).

ZAO «MSM-Invest»
34May 2010

Main pipeline of the Zapolyarniy OGCF gas condensate accumulations (Yamalo-Nenets Autonomous District). Operations environmental control.

ZAO “Yamalgazinvest”
33April - May 2010

Developing project documentation for the capital repair of the green area at 1-3, Melikhovskaya str. and Belozerskaya str. crossing (Moscow).

Prefecture of Moscow North-East Administrative District
32April - May 2010

Developing project documentation for the capital repair of the green area at the Yauza floodplain, along Severodvinskaya str. (Moscow).

Prefecture of Moscow North-East Administrative District
31March - May 2010

A set of the geodetic engineering, geological engineering, environmental engineering, and hydrometeorological engineering surveys at the reconstruction area of the ОАО «Sukhoy Company» testing facility (Moscow).

ОАО «Sukhoy Company»
30March - April 2010

A set of the environmental engineering and geological engineering surveys for the re-equipemnt and reconstruction project (OAO "Mil Moscow helicopter plant" manufacturing, Tomilino, Moscow region), phase 1, "Assembly facility reconstruction".

OAO "OPK "Oboronprom"
29January - March 2010

A set of the environmental engineering, geological engineering, and geodetic engineering surveys for the manufacturing projects at the OAO “Voronezh joint-stock aircraft manufacturing company” (Voronezh), OAO "Tupolev" (Moscow, Ulyanovsk), "KAPO im. Gorbunova" (Kazan), OAO "United Aircraft Corporation" (Moscow).

OAO "United Aircraft Corporation"
28January - March 2010

A set of the environmental engineering and geological engineering surveys for the re-equipment and reconstruction project at the machining, assembling, and blank productions, OAO "Aviastar" (Ulyanovsk).

OAO "United Aircraft Corporation"
27June - December 2009

Integrated geological engineering surveys for developing project documentation (construction of the M-5 "Ural" road from the Moscow internal ring to Ulyanino settlement (Moscow Region).

OAO "Proekttransstroy"
26June - December 2009

Integrated geological engineering for the project of ponds remeadiation and ecological rehabilitation (Moscow): 1) 15 (estate), Krasnoyarskaya str. (Golyanovo microdistrict); 2) 10 and 28 (estates), Generala Dorokhova str. (Ochakovo-Matveevskoe microdistrict); 3) 3 (estate), Sergeya Lazo str., "Sovetskiy" pond (Perovo microdistrict); 4) Butovo ponds № 1 and № 2 (Yuzhnoe Butovo microdistrict); 5) 8-10 (estates), Suzdal'skaya str. (Novokosino microdistrict); 6) 5-1, Ayvazovskogo str. (Yasenevo microdistrict); 7) 7 (estate), Akademika Artsimovicha str. (Tepliy Stan microdistrict).

ООО «Mon-Company», ООО «Kapitel'»
25November - December 2009

A set of the environmental engineering surveys and agrochemical research for developing a reconstruction project of the exhibition territory for the weaponry and navy, for the needs of the Central Museum of the Great Patriotic War (Moscow).

ООО «Center of industrial and construction design»
24October - December 2009

Chemicoanalytical analysis of the samples of naturally and technologically salinized soils and waters in the areas affected by underground storages of hydrocarbons in rock salt, including Volgogradskoe, Yar-Bishkadakskoe, Kashkarskoe, and Kazayakskoe (Volgograd Region, Astrakhan Region).

OOO "Podzemgazprom"
23October - December 2009

A set of environmental engineering surveys for site improvements at "Tsaritsyno Natural and Historical Park" from the side of Lipetskaya str. and Shipilovskiy proezd, and at the 1st district of the Biryulevskiy arboretum park (Moscow).

OOO "Akvalight"
22May - December 2009

A set of the environmental engineering surveys and gas-geochemical investigations for developing project proposals for the recultivation of the unauthorized landfill areas ("Mosvoretskiy" natural and historical park, Moscow).

The Environmental Fund for Urban Development «ECOGOROD»
21July - September 2009

A set of the environmental engineering, geological engineering, and hydrological engineering surveys for constructing a pond at the Rzhavka river (Zelenograd, Moscow).

Youth Residential Complex "Zelenograd"
20July - September 2009

A set of the environmental engineering, geological engineering, and geodetic engineering surveys for the project on manufacturing and testing facility re-equipment and reconstruction (Dubna, Moscow Region).

OAO “A.Y. Bereznyak State mechanic and engineering bureau “Raduga”
19June - August 2009

A set of geological engineering surveys for the project of environmental rehabilitation of the Setun' river from the Moscow Automobile Ring Road to theoutlet to Moscow river, including the surrounding territory within the "Setun' river valley" nature reserve.

ООО «Mon-Company», ООО «Kapitel'»
18May - July 2009

Integrated geological engineering surveys for a project of the capital repair of the Ochakovka river channel from Proektiruemiy proezd 1523 to Lobachevskogo str. (Moscow).

ООО «Mon-Company», ООО «Kapitel'»
17January - March 2009

Geological engineering, hydrogeological and environmental engineering surveys for the construction project of a water reservoir at the ПК-96 natural complex territory (Moscow).

Prefecture of Moscow East Administrative District
16January - March 2009

A set of engineering surveys for the remeadiation and ecological rehabilitation of the ponds cascade at the "Pokrovskoe - Streshnevo" natural and historical park (Moscow).

OOO "Gidrotekhnik-17"
15September 2008 - January 2009

A set of the geological engineering and environmental engineering surveys for the pre-project studies on the environmental rehabilitation of the Nevrashka river valley ("Setun' river valley" nature reserve, Moscow).

OOO "Centerstroyproekt"
14September 2008 - January 2009

A set of engineering surveys for a project of the streams capture and drain control near the "Vorobiovy Gory" nature reserve embankment (Moscow).

OOO "Centerstroyproekt"
13August- December 2008

Environmental engineering surveys for 15 recreational areas. Working project for the redevelopment of "Bitsevskiy park" natural and historical park recreational areas (Moscow).

Prefecture of Moscow South-West Administrative District
12June - December 2008

Environmental impact assessment of a land parcel. A set of the geological engineering, environmental engineering, hydrometeorological engineering surveys, and surveys of the unsurfaced material for the hydraulic structure of the recreational hotel complex (Tula Region).

ООО «Eurasia Country Format»
11June - December 2008

Developing a project of the Usinsk-Kharyaga road repair (Usinskiy district, Komi Republic).

Road agency of the Komi Republic
10August - December 2008

A set of environmental engineering surveys for the «Sakhalin-Khabarovsk-Vladivostok» gas pipeline construction project.

ОАО «NIPII ET «ENERGOTRANSPROEKT»
9August - December 2008

A project for constructing "East Siberia - Pacific Ocean" pipeline system. "Skovorodino" oil pump station - "Kozmino" specialized oil seaport. A set of environmental engineering surveys for the following oil pump stations: NPS-24, NPS-27 (Amursk Region), NPS-30 (Jewish Autonomous Region), NPS-34, NPS-36 (Khabarovsk Territory).

ОАО «NIPII ET «ENERGOTRANSPROEKT»
8August - September 2008

A set of the geological engineering and environmental engineering surveys for developing a project of the improvements and environmental rehabilitation of the ponds at Serebryanka river in Terletskiy forest-park, Izmailovo park of culture and leisure (Moscow).

ОАО «Mosinzhzelenstroy»
7March - June 2008

A project of constructing radio-relay stations for the Urengoy-Uzhgorod gas pipeline. A set of engineering surveys (Kursk Region, Tambov Region).

OAO "Mostransgaz"
6January - February 2008

A set of environmental engineering surveys at the area of constructing Olympic objects at Imertinskaya plain within the preparation to the Olympic Games (Krasnodar Territory).

OOO "Stroyrezerv"
5January - February 2008

Integrated soil-ecological research at a section of the operating Vargashi-Suslovo oil pipeline (Kurgan Region).

OOO "Stroyrezerv"
4September - November 2007

Integrated environmental engineering soil, ground, and bottom materials surveys at the Yauza river valley (Moscow).

Prefecture of Moscow North-East Administrative District
3July - November 2007

A series of the thematic maps for the part of the environmental impact assessment for the construction of hydroelectric power chain at the Timpton river (feasibility study stage), Republic of Yakutia.

OOO "Stroyrezerv"
2February - May 2007

A project for constructing Unecha-Primorsk oil pipeline (Baltic pipeline system БТС-II). Environmental soil surveys at the oil pipeline segments in the Bryansk, Smolensk, Tver, and Leningrad Regions. A series of the thematic maps for the part of the environmental impact assessment.

OOO "Stroyrezerv"
1December 2006 - February 2007

A set of the environmental engineering and geological engineering surveys for a project of the ecological rehabilitation of the "Setun' river valley" natural reserve along Davydkovskaya str. (Moscow).

OAO "Mosinzhlenstroy"